1. BASE PREPARATION

For base preparation, level and clear the area, then excavate and compact allowing for grid thickness and an additional 10mm surface dressing of aggregate. Level the surface with 10-20mm of sharp sand to ensure a smooth base. Sand base is optional.

2. PLACE THE PANELS

Lay the panels with the geotextile face down, aligning the first row against a stationary edge if possible. Cut to shape wearing protective gloves to avoid abrasions. Stagger panels in a bricklayer pattern and clip together using the interlocking connectors on all sides to form one continuous matrix.

Ensure the overlapping edge of the attached geotextile membrane is flat to receive the next panel. The panels should should sit 10mm below the adjacent surface to allow for gravel coverage. GD Gravel can be laid on slopes up to 20 degrees without the need for any additional ground pegs.

3. FILL THE CELLS

Infill gravel or aggregate into the hexagon cells by hand, or directly from a truck. Trucks should be careful to avoid sharp turns on unfilled panels.

Preferably the truck should dump gravel first on the edge of the installation area, then work inward, therefore only driving on filled cells. Gravel can be spread by hand with flat shovels, rakes, blades, or stiff brooms.

4. SMOOTH SURFACE

Level the gravel or aggregate to cover the panels by 10mm so that they are just out of sight. This allows for aesthetics, stability and protection. Optionally, a vibrating compaction plate or roller can be used to set the gravel into the cells.


Click Here for more GD Gravel Resources.

We deliver Green Driveway products across North America and into Mexico.


Contact us for an estimate or to purchase our materials for your personal or civic project.